Are you guys looking for Civil Engineering MCQ Questions with Answers PDF Free Download as per Civil Engineering new exam pattern? You came to the right page. This may assist you to understand and check your knowledge about the Subjects. Students also can take a free test of the Multiple Choice Questions of Civil Engineering. Each question has four options followed by the right answer. These Civil Engineering MCQ Questions are selected supported by the newest exam pattern.
Q1. Pick up the incorrect statement from the following:
(A) Cement is added to lime mortar to increase its hydraulic properties only
(B) Lime surkhi mortar is used for pointing the walls
(C) Lime should be slaked before preparing lime mortar
(D) High early strength concrete is generally used in cold weather
Answer: (A) Cement is added to lime mortar to increase its hydraulic properties only
Q2. The minimum thickness of walls built in cement mortar (1 : 6) for a single storey building, is
(A) 10 cm
(B) 15 cm
(C) 20 cm
(D) 25 cm
Answer: (C) 20 cm
Q3. The 9 cm × 9 cm side of a brick as seen in the wall face, is generally known as
(A) Stretcher
(B) Face
(C) Front
(D) Header
Answer: (D) Header
Q4. Pile foundation is generally provided if soil is
(A) Compressible
(B) Water logged
(C) Made up
(D) All the above
Answer: (D) All the above
Q5. Pick up the commonly adopted geophysical method in civil engineering from the following:
(A) The seismic method
(B) Electrical resistivity method
(C) Gravitational method
(D) Both (a) and (b) of the above
Answer: (D) Both (a) and (b) of the above
Q6. The range of spread from the wall base to outer edge of a brick work foundation does not exceed
(A) 1/2 horizontal to 1 vertical
(B) 2/3 horizontal to 1 vertical
(C) 1 horizontal to 1 vertical
(D) 2 horizontals to 1 vertical
Answer: (C) 1 horizontal to 1 vertical
Q7. Bearing capacity of soils cannot be improved by
(A) Draining sub-soil water
(B) Ramming crushed stone in soil
(C) Driving sand piles
(D) Watering surface of soil
Answer:(D) Watering surface of soil
Q8. If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is
(A) 12
(B) 18
(C) 24
(D) 25
Answer: (C) 24
Q9. The foundation in which a cantilever beam is provided to join two footings, is known as
(A) Strip footing
(B) Strap footing
(C) Combined footing
(D) Raft footing
Answer: (B) Strap footing
Q10. Rotary drilling is the fastest method in case of
(A) Rocky soils
(B) Clay soils
(C) Sandy soil
(D) All of these
Answer: (D) All of these
Q11. Dado is usually provided in
(A) Dining halls
(B) Bath rooms
(C) Living rooms
(D) Verandah (belcony)
Answer: (B) Bath rooms
Q12. Auger boring
(A) Is the most primitive method for making a hole in the ground
(B) Is generally employed in cohesive and other self soils above water table
(C) Is most economical up-to a depth of 5 meters
(D) All the above
Answer: (D) All the above
Q13. The concrete slump recommended for beams and slabs; is
(A) 25 to 50 mm
(B) 25 to 75 mm
(C) 30 to 125 mm
(D) 50 to 100 mm
Answer: (C) 30 to 125 mm
Q14. A roof which slopes in four directions, is called
(A) Shed roof
(B) Gable end roof
(C) Hipped roof
(D) Gambrel roof
Answer: (C) Hipped roof
Q15. In horizontal D.P.C, thickness of cement concrete (1 : 2 : 4) is
(A) 2 cm
(B) 4 cm
(C) 6 cm
(D) 8 cm
Answer: (B) 4 cm
Building Construction MCQ SET wise with Answers
- Building Construction MCQ SET-1
- Building Construction MCQ SET-2
- Building Construction MCQ SET-3
- Building Construction MCQ SET-4
- Building Construction MCQ SET-5
- Building Construction MCQ SET-6
- Building Construction MCQ SET-7
- Building Construction MCQ SET-8
- Building Construction MCQ SET-9
- Building Construction MCQ SET-10
- Building Construction MCQ SET-11
- Building Construction MCQ SET-12
- Building Construction MCQ SET-13
- Building Construction MCQ SET-14
- Building Construction MCQ SET-15
- Building Construction MCQ SET-16
- Building Construction MCQ SET-17
- Building Construction MCQ SET-18
- Building Construction MCQ SET-19
We hope the given Civil Engineering MCQ Questions with Answers will definitely yield fruitful results. Hope you got enough ideas on the MCQs on Civil Engineering. If you have any queries related to Civil Engineering MCQs Multiple Choice Questions with Answers, drop your questions below and will get back to you in no time.